Just like as death and taxes are the
only certainties in our lives, the only
certainty in a life of a project is the
occurrence of one or more risks. In this
chapter we will try to see how we could guard
against these risks in a project by anticipation,
right assessment and detailed strategy
for handling them as and when they occur.
What are risks?
Risks are typically unforeseen events,
which can cause adverse impact to any
project. Risks can happen to any one of
the major parameters of a project namely
its schedule, scope, resources and quality.
Risks are the ones, which give credence
to all the Murphy's laws you hear and
generally make the life of a project manager
interesting.
Are they a certainty?
Yes. They are. If things can grow wrong,
they will. When they go wrong they seem
to go wrong absolutely! All experienced
project managers would vouch for the certainty
of risks in projects.
Is there a way to plan for managing
risks?
Yes. Planning for a risk includes the
following activities:
Anticipate and identify all potential
risks, which can happen
Associate
a probability with each of the identified
risk
Make
an impact assessment if the identified
risks were to happen
Have
a mitigation / contingency plan for each
of the identify risks
Watch
out for the early signs
Understand
the effectiveness of the contingency plan
and refine accordingly
Update
risk database as unanticipated risks happen
How does one anticipate and identify
risks in a project ?
Risk anticipation comes with experience.
But even a novice project manager can
anticipate risks in a project. Some of
the risks which normally occur in a in
a project are:
People may leave the project mid
way (attrition)
Complexity of a task is under estimated
Customer may cancel the order
An Earthquake may happen which can have
a telling effect
And the list goes on. One of the things
a project manager needs to do is to associate
the risks with a specific parameter of
a project. For instance employee attrition
is a resource risk. But it is likely to
have an impact on schedule and even the
scope of the project if the risk is not
handled. Release of a competitor's product
ahead of schedule is a schedule risk for
your project, which again may impact the
scope of your project and might necessitate
a manager to add more resources.
In planning for risks, experience is
the best teacher. One of the things a
project manager can do is to find out
similar projects done in the past and
import their risk database to his/her
project. This way (S) he could leverage
from the experience of other projects
and project managers. Smartworks - Project
Planner has the following option, which
allows you to do this with ease. To do
this the project manager needs to export
the risk database of a similar project
as shown below
Fig1.1: Exporting
risk database of a project |
The risk database of a project is saved
usually with a .rsk extension Now you
log in to your current (new) project and
import the risk database as shown below.
Fig1.2: Importing
the Exported risk database of a
project |
In case if you are not able to find a
similar project you need not despair. Smartworks
Project Planner comes with a default
risk database which can be used in your
project.
Fig1.3: Default
risk database |
How does one arrive at a probability
of occurrence for the risks we have identified?
While there can be thousands of risks
which can happen to a project not all
risks are likely to happen. Some risks
have a higher probability than others.
For instance earthquake is a risk which
when happens may have a deadly impact
on a project but is less likely to happen
compared to attrition in a project. (May
be if the location is prone to earth quakes
then this might not be true!)
In general the following risks are likely
to have a high probability of happening
in any project which spans for a year
or more.
Employee takes unplanned vacation
(falls sick). - Resource risk
Customer adds new requirements after they
are frozen. - Scope risk
Marketing wants you to release the product
ahead of schedule - Schedule risk
Following are some of the risks which
may have a low probability of occurrence
New invention/technology renders
the product obsolete
Political instability in a supplier's
country affects supply of raw materials
All the project members meet with an accident
during a company vacation
And there are hundreds of risks which
have a medium probability of occurrence.
It should be borne in mind that probability
of risk occurrence is not static and it
can change depending on situations. For
instance a medium probability risk "
Supplier delays shipping raw materials"
becomes a high probability risk when an
associated risk "Political instability
in a supplier's country affects supply
of raw materials" really happens.
This also illustrates how the risks themselves
are related to each other.
A project manager needs to arrive at
the risks and associate a probability
of occurrence to each of the risks. The
probability thus arrived at needs to be
revisited periodically and updated.
Project manager needs to be bothered
with the risks, which have a higher probability
of occurrence. Once high probability risks
are arrived at then the project manager
needs to study the impact of each of these
risks if they were to happen. Based on
the probability and the impact of the
risks the project manager needs to come
up with the mitigation / contingency plans
for each of these risks.
SmartWorks Project Planner currently lets the
user classify the probability of risks
into 3 categories namely high , medium
and low. This can be done by the project
manager by performing the following operations.
Fig1.4: Dialog
box which shows how probability
of a risk can be edited by manager
|
How can we assess the impact of
each of the identified risks in our project
?
Each of the risk has an impact (usually
adverse) in a project. Some of the risks
have a much higher impact on the project
health than the other ones. Some of the
risks which has a high impact in a project
are
Attrition of a critical person mid
way in a project
The schedule of a project gets compressed
by 25% due to market pressure Budget exceeded
for the project
The above risks , when they occur have
a telling impact on project's health.
While in some cases they may result in
the total cancellation of the project
, it might at least affect the scope and
the quality of the final deliverables
to the customer.
There are other risks in a project which
may have a lower impact . Some of them
could be
Employee reports sick for a day
Customer makes a minor modification to
scope
Marketing wants the product to be released
1 week ahead of planned schedule.
Not all the risks, which may have high
impact, are necessary to be worried at.
For example when a tornado strikes the
impact is going to be high but if you
are not in tornado prone areas that risk
is as good as not there. So what is really
important is the combination of the probability
of a risk and the impact of it rather
than the impact of the risks alone.
Smartworks Project Planner currently
lets the user classify the impact of risks
into 3 categories namely high , medium
and low. This can be done by the project
manager by performing the following operations.
Fig1.5: Importing
the Exported risk database of a
project |
How can one make an effective
contingency or mitigation plan for identified
risks?
Project manager needs to have a plan
to handle risks whenever they happen.
These plan needs to be planned in advance
and not when the risks happen as the manager
will not have any time to react to the
situation. For instance a project manager
needs to have extra people in the team
to handle attrition in a project. If this
plan was not there in the first place
and if he has to recruit a person to handle
any attrition as and when it happens the
project would be in disarray soon.
Let us see some examples of contingency
plan:
a) Risk name: There
is a possibility of more non RSVPed invitees
turning in for the party
Contingency plan : Ensure
that there are 10% more seats available
and the caterer can handle 10% overflow
of guests for the party.
b) Risk name : There
is only one person identified for evaluation
due to resource constraints.
Contingency plan : Make
developers aware of this fact and let
them take the responsibility for unit
testing including writing unit test plans.
Identify one of the developer who finishes
his/her task early in the team to join
the evaluation team during formal evaluation
phase
As you can see a risk has to be anticipated
in advance in order to effectively handle
it. These contingency plans do not prevent
a risk from happening but soften the blow
when it comes.
Fig1.6: Risk
database of the dream house project
|
The major challenges faced by the project
manager during this phase are staffing
(getting the right people would ensure
the success of the project) and predicting
potential risks and coming with the appropriate
back up strategies for risk mitigation.
How does one watch out for the
early signs of risks in a project?
This is one question which stumps even
the more experienced project managers.
It is essential for the project manager
to actively look for signals and interpret
them accordingly. It is not very different
from listening to seismic activities in
a region and predicting potential earth
quakes in advance. ( and it is as effective!).
For instance if an employee takes more
frequent leaves and changes the incoming
out going time then he/she is a sending
a signal to the manager. It is the responsibility
of the project manager to catch this signal
and do an analysis and some times confront
the situation.
The faculty of catching and interpreting
various signals comes with experience.
How do we know the effectiveness
of a contingency plan?
Contingency plans exist to soften the
blow. If it does not do that then the
contingency plan is not an effective one.
For example let us consider the following:
You have a supplier A who usually supplies
you the raw material required for making
your product. As a backup plan let us
assume that you have Supplier B who could
supply you the raw materials in case if
supplier a is not able to meet your requirements.
So your risk and contingency plan would
some what look like this:
risk : Supplier A is not able to meet
our total requirements
contingency plan: Identify an alternate
Supplier B who could fulfill your requirements
and intimate him to supply the materials
required as soon as you sense this risk.
Let us assume that supplier A is not able
to supply your entire demand and hence
you are forced to kick in your contingency
plan. It is possible that supplier B whom
you have identified as a back up supplier
fails to meet your requirements in terms
of turn around time, quality or both.
In this case your contingency plan has
proved to be ineffective. In such cases
you need to declare that the contingency
plan is ineffective (and possibly communicate
to the higher ups to prevent such reoccurrence)
and come up with another contingency plan
which could prove to better.
In what ways of the project
do risks usually occur?
This is a easy question to answer. They
occur in all the phases of the projects.
However risks occurring during the early
stages of a project is always easier to
handle than the ones which occur during
the later stages of the project.
What risk are common
during project planning phase?
Some of the risks which can happen during
the project planning phase are:
a) Activities are not broken down to
manageable tasks. If task duration exceeds
3 weeks then it is a candidate for further
break down. A task, which has a long duration,
has the inherent capability of throwing
up surprises to the manager at the end
of the task duration. Recovering from
a task slippage becomes more difficult
when the task duration is more than two
to three weeks. It is recommended that
project managers try to have a task whose
duration is with in a week. That way they
would know about the progress or lack
of it in the status report.
b) Assigning multiple owners for a task.
Even though practically no project manager
nowadays makes this mistake, it could
be deadly if the project manager by a
poor communicates ends up with situation.
c) Not using risk databases of previously
executed projects when starting a similar
project. Using risk databases is the best
way of leveraging other's experience in
your project. Otherwise the project manager
would be in a situation where he will
be condemned to repeat the mistakes made
elsewhere in the company.
d) Not setting the project calendar to
reflect reality. Project managers often
forget company holidays and planned vacations
of team members while making the plan
for the project. In addition to that some
allowance needs to be given for sick leaves
by the manager. Failing to set the project
calendar with all the holidays/leaves/vacation
can put enormous strain on the schedule
at a later time during the project execution
e) Coming up with the no or poor contingency
plan for the risks in a project. A risk
database is useful only when it is complete
in all aspects. The most important part
of the risk database is the contingency
plan, which the project manager needs
to have for each of the anticipated risk.
A poorly thought contingency plan would
be ineffective in the event of a risk
happening.
f) Not using historical data for estimating
tasks duration. When planning for activities
a project manager needs to use historical
data to have picture, which is closer
to reality. There are times when an activity
may not have a historical data associated
with it. In such cases it would be prudent
for the manager to have Delphi estimates
for the tasks.
What risk are common
during analysis & design phase of
a project?
Some of the risks which can happen during
this phase are:
a) Not having the right expertise. This
phase depends on experts who have adequate
technical knowledge in the project domain.
Not having experts can be devastating
to the project. Several project managers
have issues in involving external experts
during this phase of the project even
if they do not have any local experts.
But this would prove costly during the
later stage of the project. It is important
for the project manager to have the right
experts (with proper credentials) to participate
actively during this phase of the project.
b) Not enough time allocated for reviewing
which results in improper review. Review
is a critical aspect during any phase
of the project. However it assumes more
significance during this phase of the
project as the blue print of the whole
project is generated during this phase.
Improper review during this phase spells
doom for the project.
c) Not listening to devil's advocate.
Project managers sometime end up finalizing
a design without a complete analysis.
Project managers and most of the team
members want to move over to the implementation
phase of the project as quickly as possible
due to the fear of slipping schedule.
When they have this mind set they are
not open to a critical review of the design
where in major flaws are pointed out.
Failure to listen to comments from such
devil's advocates can jeopardize the success
of the project.
What risks are common
during implementation phase of a project?
Some of the risks which can happen during
this phase are:
a)Poor monitoring of progress:
Project managers some times tend to spend
most of their time in planning activity
and surprisingly very less time in following
up whether the implementation is following
the plan. A proactive report generated
by Smartworks-Project planner can really
help the project manager to know whether
the tasks are progressing as per the plan.
Fig1.7: Sample
Project Summary report |
During this phase a project manager
is likely to get many alerts whenever
a task slippage occurs. It is important
for the project manager to understand
the reason for slippage and take corrective
actions. For instance smartworks project
planner provides such alert notifications
through emails. A sample alert for a task
slippage would be some what like this:
Fig1.8: Sample
email alert report |
In addition to the reports and alerts
you may use SmartWorks project planner's
gantt chart and project graphs to get
a better picture of the project.
b)Not handling risks:
Risks have an uncanny habit of appearing
at the least expected time. In spite of
the best efforts of a project manager
they are bound to happen. Risks need immediate
and focused attention. Delay in dealing
with risks cause the problem to aggravate
and has negative consequences for the
project.
c)Poor cost management:
A manager's success is measured by the
amount of cost optimization done for a
project. Managers frequently do all the
cost optimization during the planning
stages but fail to follow through during
the rest of the stages of the project.
The cost graphs in the Smartworks- Project
planner can help a manager to get a heads
up in project cost overflow. The cost
variance (The difference between approved
cost and the projected cost should be
always in the minds of the project managers).
Fig1.9: Sample
project Cost Graph |
What risk are common
during project end phase
Some of the risks which can happen during
this phase are:
a)Not having immediate post mortems:
Some of the project managers want to solve
current problems. A post mortem essentially
focuses on past problems. Hence they fell
that it is not important and often do
not hold them in the first place or even
if they hold it they ensure that every
body knows that it is only a ritual. While
post mortem indeed talk about past problems
in a project they are the best places
to identify unsolved critical problems
and potential future problems which is
going to have a telling effect on other
projects
b) Not getting customer feedback:
It is vital for project managers to get
a feedback from the customer once the
project is completed. Typically this should
happen when the customer has really started
using the deliverables from the project.
Getting this feedback provides the managers
with a user's perspective which is the
most important (s) he would ever get about
the project's success. Some of the project
managers do not get feedback and lose
the immense benefit it can bring to future
projects.