Project Health
- How do project graphs help us to get
this picture ?
A Project typically has several parameters
which needs constant attention. In order
to monitor the health of a project, managers
need various visual indicators which would
help them overcome the several uncertainties
in a project. In this paper we will discuss
some of these visual indicators(project
graphs) which help managers to get a good
feel of the project's overall health.
Any project management package ( e.g. Smartworks Project Planner ) provides the managers
with various graphs to monitor progress
of projects. Gantt charts , Network diagrams
are some of the popular means managers
employ to get a good feel of where the
projects are heading. However in this
paper we would be looking at other graphs
which can also throw vital clues to project
health.
1. Project Estimate Graph
Most of us would like to have a crystal
ball to predict future. This need is more
acute for project managers. The project
estimate graph presented by Smartworks
Project Planner fulfills this need of
the project planner to some extent. Essentially
it predicts when a project would end based
on the current progress made in the project.
The accuracy of these graphs improve over
time in a project. So these estimate becomes
more reliable as we cross a half way mark
in a project.
Fig1.1: Project
Estimate Graph |
In the above graph the dotted line indicates
the estimated date of completion of the
project while the rigid line indicates
when the project would complete as per
the plan. A healthy project would have
the variation between the planned and
the projected to be less than 15% of the
overall schedule. However if the variation
is more than that it is a heads up for
the project manager to take appropriate
action.
2. Total tasks Vs task status
( How much of the project is complete?)
This graph gives a bird's eye view of
how much of the project is already done.
It gives you a pie chart with tasks arranged
in the order of completion ( varying from
new task , partially completed task and
completed tasks). In the case of Smartworks
project planner the new tasks are shown
in the RED color. Hence if your pie chart
is mostly red then you have a long way
to go in terms of project completion.
Fig1.2: Total
task vs Task status graph
|
A word of caution. The pie chart lists
the number of tasks and the associated
task status. It has no means of knowing
the complexity of the task. So it is possible
that lots of simple tasks in a project
could have been completed while most complex
tasks are not even started. This could
give a feeling to the project manager
that things are OK when it is really not.
A possible future improvement which can
be done in smartworks project planner
is to have the duration of the tasks also
to be considered while computing the pie
chart. This could give a better picture
than what is done currently.
3.Total tasks Vs User (How are
tasks distributed in the project?)
This graph gives a good overview of how
various tasks are distributed among the
project members. It also gives an idea
of how each of the project members have
progressed so far. This graph gives the
following details for each of the project
members :
Total
tasks assigned to them (Blue)
Total
tasks completed by them so far (Green)
Total
tasks which are yet to be completed
(Red)
|
Fig1.3: Total
tasks vs Users |
These graphs give a project manager a quick
way to assess the work distribution and
to plan remedial action in case some members
are struggling with their assigned work.
4. Total task vs completion time
(Are we completing on time?) ?
There is a common saying that a 1 year
delayed project got delayed one day at
a time. Project managers often need to
have a look at how well tasks were completed
in a project with respect to a given schedule.
If more number of tasks (even if they
are not critical) get delayed it could
result in the eventual delay of the project.
Not keeping up the schedule is a disease
in a project which spreads quickly.

Fig1.4: Total tasks vs Completion
time |
In the graph you have number of tasks
listed in the Y axis. On the X axis you
have bar charts representing tasks with
pre defined slippage ranging from 0 (on
time) to (incomplete) encompassing various
time duration such as slippage by a day,
week, month, 6 months and a year. A project
manager is happy to see majority of the
tasks to be completed on time or within
a week slippage.
5. Users Vs completion time (
which team members normally finish on
time?)
A project manager needs to identify team
members who are likely to finish their
tasks on time.
Procrastination is a habit and it is better
for the project manager to identify which
of his/her team members have this habit.
The Users Vs completion time graph gives
a petty good picture of this.

Fig1.5: Users Vs Completion time |
Project managers can use the above graph
to take corrective actions by monitoring
people who slip in most of the tasks assigned
to them, redistribute tasks, preplan tasks
in case the task's complexity had been
under estimated before.
6. Cost graphs
All project managers have a budget for
their project. Project manager always
should have a tab of how much money had
been already consumed at any given time
in a project. This piece of information
helps the manager to control unwanted
expense and ensure that the project does
not overshoot the allocated budget.
Fig1.6: Cost
Graph |
Smartworks
Project Planner graph allows managers
to view project costs in terms of hours,
days, weeks, months and for the complete
project duration as well. Managers can
track the cost incurred by a specific
resource or for all the resources in a
project. A provision to set up a cost
threshold for the project manager to be
alerted would have been useful. Perhaps
they might provide this in a future version
of their product.